Designated Structure Permit: Retaining Wall, Solar, Antenna or Wind Turbine (Pickering)
Pickering building permit for designated structures such as public-facing retaining walls over 1 m, solar panels, radio antennas and wind turbines over 3 kW [pickering.ca].
You need it when: You build a retaining wall over 1 m next to public property, or install solar panels, a green roof, a radio antenna or a wind turbine over 3 kW in Pickering.
Why is it needed?
- Pickering requires a permit for a retaining wall over 1 m next to public property or areas open to the public [pickering.ca].
- Solar panels and collectors, green roofs, radio antennas and wind turbines over 3 kW also need a permit [pickering.ca].
- Private retaining walls under 1 m need no permit, but zoning still applies [pickering.ca].
When should you apply?
- Some properties need approvals from agencies such as TRCA, CLOCA or Durham Region Health before a building permit is issued [pickering.ca].
- Once the permit is issued, construction may start any time within 6 months [pickering.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Radio antenna form CDD1205 for an antenna [pickering.ca]
- Commitment to General Reviews form [pickering.ca]
- Schedule 1 Designer Information form [pickering.ca]
- Agent Authorization form CDD1605 if a designer or contractor applies for you [pickering.ca]
How do you submit it?
- Call Building Services at 905.420.4631 to start, then apply through the Permit Submission Portal at mycity.pickering.ca [pickering.ca].
- Applications are fully electronic, printed copies are no longer accepted at the counter, and drawings sent by email are not accepted [pickering.ca].
What are the fees?
2026 fee: solar or wind $305.20 (Schedule of Application Fees, July 1, 2026) [pickering.ca].
Forms and guides
- Pickering Schedule of Application Fees and Information Price List (July 1, 2026) (City of Pickering, fee schedule)
- Pickering Schedule 1 Designer Information Form (City of Pickering, application form)
- Pickering Commitment to General Reviews by Architect and Engineers (City of Pickering, application form)
- Pickering Radio Antenna Form (CDD1205) (City of Pickering, application form)
- Pickering Agent Authorization (CDD1605) (City of Pickering, application form)
Official pages
Track Designated Structure Permit: Retaining Wall, Solar, Antenna or Wind Turbine (Pickering) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.