Building Permit: Large Building, Part 3 (Pickering)
Building permit from Pickering Building Services for a Part 3 building, under the Ontario Building Code and the City's Building By-law, with fees by occupancy group [pickering.ca].
Why is it needed?
- Pickering requires a building permit for new buildings and additions [pickering.ca].
- Plans must meet the Ontario Building Code, the zoning by-law and other applicable law [pickering.ca]. The Ontario Building Code, O. Reg. 163/24, applies in every Ontario municipality [ON].
When should you apply?
- Use the Applicable Law Checklist (CDD1206) to confirm the other approvals that must be in place before a building permit can be issued [pickering.ca].
- Agencies such as TRCA, CLOCA, MTO, Durham Region Health, the Ministry of Education or the Ministry of Long-Term Care may need to approve before you apply or before occupancy [pickering.ca].
- The permit is issued once all fees, deposits and charges are paid and Building Code compliance is confirmed, and construction may start any time within 6 months of issue [pickering.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Ontario Application for a Permit to Construct or Demolish, filed in the Permit Submission Portal [pickering.ca]
- Commitment to General Reviews form [pickering.ca]
- Schedule 1 Designer Information form and Applicable Law Checklist (CDD1206) [pickering.ca]
- Seniors Residential Facility Checklist for a retirement residence [pickering.ca]
- Agent Authorization form (CDD1605) if a designer or contractor applies for the owner [pickering.ca]
How do you submit it?
- Call Building Services at 905.420.4631 to start, then apply through the Permit Submission Portal at mycity.pickering.ca [pickering.ca].
- Drawings sent by email and printed copies are no longer accepted, and fees can be paid in the portal or at the counter at One The Esplanade [pickering.ca].
What are the fees?
2026 fee per m2 of gross floor area: Assembly $33.88, Care $38.75, Residential $20.12 (1 to 20 storeys), business and mercantile $21.38 single storey or $26.50 multi-storey, industrial $8.75 to $15.88 (Schedule of Application Fees, July 1, 2026) [pickering.ca]. An initial minimum fee is billed at submission and later bills are emailed at each stage of review [pickering.ca].
Forms and guides
- Pickering Schedule of Application Fees and Information Price List (July 1, 2026) (City of Pickering, fee schedule)
- Pickering Guide to Online Building Permit Applications (City of Pickering, guide)
- Pickering Applicable Law Checklist (CDD1206) (City of Pickering, checklist)
- Pickering Schedule 1 Designer Information Form (City of Pickering, application form)
- Pickering Commitment to General Reviews by Architect and Engineers (City of Pickering, application form)
- Pickering Acknowledgement of Incomplete Application (City of Pickering, application form)
- Pickering City Expectations for Builders (City of Pickering, guide)
- Pickering Agent Authorization (CDD1605) (City of Pickering, application form)
- Pickering Seniors Residential Facility Checklist (City of Pickering, checklist)
Official pages
- Building permits in Pickering
- Commitment to General Reviews form (PDF)
- Schedule of Application Fees, July 1, 2026 (PDF)
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.