Building Permit: Complex Building, High-rise or High-hazard (Pickering)
Building permit from Pickering Building Services for a complex building such as a high-rise, under the Ontario Building Code and the City's Building By-law [pickering.ca].
You need it when: You build a high-rise, a post-disaster building or a high-hazard industrial building in Pickering.
Why is it needed?
- Pickering requires a building permit for new buildings and additions, and plans must meet the Ontario Building Code, the zoning by-law and other applicable law [pickering.ca].
- The Ontario Building Code, O. Reg. 163/24, treats high buildings and high-hazard industrial buildings as complex buildings [ON].
When should you apply?
- Use the Applicable Law Checklist (CDD1206) to confirm the other approvals that must be in place before a building permit can be issued [pickering.ca].
- Some properties have extra requirements to meet before a building permit is issued, and agencies such as TRCA, CLOCA, MTO or Durham Region Health may need to approve before you apply [pickering.ca].
- The permit is issued once all fees, deposits and charges are paid and Building Code compliance is confirmed, and construction may start any time within 6 months of issue [pickering.ca].
How long does review take?
Plan for about 30 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Ontario Application for a Permit to Construct or Demolish, filed in the Permit Submission Portal [pickering.ca]
- Commitment to General Reviews form [pickering.ca]
- Schedule 1 Designer Information form and Applicable Law Checklist (CDD1206) [pickering.ca]
- Agent Authorization form (CDD1605) if a designer or contractor applies for the owner [pickering.ca]
How do you submit it?
- Call Building Services at 905.420.4631 to start, then apply through the Permit Submission Portal at mycity.pickering.ca [pickering.ca].
- Drawings sent by email and printed copies are no longer accepted, and fees can be paid in the portal or at the counter at One The Esplanade [pickering.ca].
What are the fees?
2026 fee for residential buildings per m2 of gross floor area: $21.82 for 21 to 40 storeys and $23.58 for 41 storeys or more (Schedule of Application Fees, July 1, 2026) [pickering.ca]. Other occupancies are charged by group per m2 under Part B of the same schedule [pickering.ca].
Forms and guides
- Pickering Schedule of Application Fees and Information Price List (July 1, 2026) (City of Pickering, fee schedule)
- Pickering Guide to Online Building Permit Applications (City of Pickering, guide)
- Pickering Applicable Law Checklist (CDD1206) (City of Pickering, checklist)
- Pickering Schedule 1 Designer Information Form (City of Pickering, application form)
- Pickering Commitment to General Reviews by Architect and Engineers (City of Pickering, application form)
- Pickering Acknowledgement of Incomplete Application (City of Pickering, application form)
- Pickering City Expectations for Builders (City of Pickering, guide)
- Pickering Agent Authorization (CDD1605) (City of Pickering, application form)
Official pages
Track Building Permit: Complex Building, High-rise or High-hazard (Pickering) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.