Region of Peel Water / Wastewater Service Connection Approval
Written approval from Peel's Servicing Connections team, needed before the local municipality issues the building permit [PEEL].
You need it when: Connecting, changing or disconnecting a property's service to Peel's municipal water, wastewater or regional storm sewer system.
Why it's needed
- Peel must approve all connections to its water, wastewater and regional storm systems [PEEL].
When to apply
- Before the building permit. Review: 20 business days for the first ICI submission and 14 for resubmissions (residential: 7 and 3) [PEEL].
- Give at least 5 business days' notice before construction; get locates through Ontario One Call [PEEL].
Review time
Plan for about 20 business days. ICI first submission [PEEL]
Documents for a complete application
- Site servicing drawings (PDF) meeting Peel and OPS standards [PEEL]
- Water/wastewater demand table if capacity modelling is needed [PEEL]
- Stormwater management report and grading drawings next to regional roads [PEEL]
- Water meter size shown on the drawings [PEEL]
How to submit
- servicingconnections@peelregion.ca; 905-791-7800 ext. 7973 [PEEL].
Fees
Submission fee $750 ICI / $400 residential; $360 per extra engineering review; meter, test-and-tap and inspection charges; refundable securities $2,500–$10,000 (2026) [PEEL].
Forms and guides
- Region of Peel Stormwater Design Criteria and Procedural Manual (Region of Peel, standard / specification)
Official pages
Track Region of Peel Water / Wastewater Service Connection Approval free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.