Region of Peel CLI ECA Sewer Extension Forms (SS1/SS2)

Under O. Reg. 208/19, developers extend Peel's system under the Region's Consolidated Linear Infrastructure ECA, documented on Forms SS1/SS2 with Peel's consent, instead of getting a separate MECP ECA [PEEL].

You need it when: Extending or altering Peel's wastewater system (sanitary sewers, forcemains, pumping stations), e.g. new sewers in a development that Peel will own.

Why it's needed

When to apply

Review time

Plan for about 30 business days. estimate

Documents for a complete application

How to submit

Official pages