Part Permit: Superstructure
Allows superstructure construction after the foundation part permit, before the full permit.
You need it when: Superstructure work must start before the full building permit.
Why it's needed
- Used when superstructure work must start before the full building permit.
When to apply
- After the foundation part permit. HVAC permits need the superstructure (or full) permit review completed first.
Review time
Plan for about 90 business days.
Documents for a complete application
- Superstructure drawings (architectural/structural)
- OBC code analysis
- Toronto Building application checklist for the permit type (ask for the latest version at pre-application)
Submission checklists
How to submit
- Electronic submission to Toronto Building.
Forms and guides
- Application for a Permit to Construct or Demolish (City of Toronto, application form)
- Commitment to General Reviews by Architect and Engineer (City of Toronto, declaration)
Official pages
Track Part Permit: Superstructure free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.