Part Permit: Superstructure

Allows superstructure construction after the foundation part permit, before the full permit.

You need it when: Superstructure work must start before the full building permit.

Why it's needed

When to apply

Review time

Plan for about 90 business days.

Documents for a complete application

Submission checklists

How to submit

Forms and guides

Official pages

Track Part Permit: Superstructure free.
Deadlines in business days, email alerts before decisions are due, and your whole team in one place.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.