Permit Library › Other GTA municipalities › City of Oshawa › Building permits (Building Permit Services)
Sign Permit (Oshawa)
Building permit for a sign structure in Oshawa, governed by Sign By-law 72-96 and designed to Part 4 of the Ontario Building Code [oshawa.ca].
You need it when: You put up or change a fascia, ground, canopy, pylon, projecting or banner sign, an LED message board or a billboard in Oshawa.
Why is it needed?
- A building permit is required for fascia, ground, canopy, pylon, projecting and banner signs, LED message boards (read-o-graphs) and billboards [oshawa.ca].
- No permit is needed for an incidental sign of 0.4 m2 or less, a window sign inside a window or door, or a temporary home builder ID, real estate open house or community event sign that complies with the by-law [oshawa.ca].
- Sign structures are designed to Part 4 of the Building Code, and an architect or professional engineer designs and field reviews them where Div. C requires [oshawa.ca].
When should you apply?
- A sign that does not comply with Sign By-law 72-96 needs a sign variance, applied for through the portal at servicecv.oshawa.ca/Planning/Application [oshawa.ca].
- Where general review applies, the owner commits to have it carried out by an architect or professional engineer [oshawa.ca].
How long does review take?
Plan for about 10 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application to construct or demolish (Ontario 2026 form) [oshawa.ca]
- Owner's authorization form if you are not the owner, and Schedule 1 designer information [oshawa.ca]
- Applicable law form, and the commitment to general review where it applies [oshawa.ca]
- Site plan or survey of the whole property with lot dimensions, sign location, dimensions and setbacks. An up-to-date OLS survey may be required [oshawa.ca]
- Structural plans with design wind force, soil bearing capacity, soil type, sign face material, and member sizes, grades and connections [oshawa.ca]
How do you submit it?
- Apply through the building permit portal at servicecv.oshawa.ca/Permit/Application [oshawa.ca].
What are the fees?
Building permit fees are set in Building By-law 33-2009 from page 16 and rose 3% on January 1, 2026. The exact cost is calculated when you apply [oshawa.ca].
Forms and guides
- Oshawa Building By-law 33-2009 (as amended by By-law 118-2025) (City of Oshawa, by-law)
- Oshawa When Do I Need a Building Permit (City of Oshawa, guide)
- Oshawa Basic Building Permit Requirements (City of Oshawa, checklist)
- Oshawa Applicable Law Checklist (City of Oshawa, checklist)
- Oshawa Sign By-law 72-96 (City of Oshawa, by-law)
Official pages
Track Sign Permit (Oshawa) free.