Consent to Sever: New Lot (Oshawa)
Consent to sever land into a new lot, decided by the Oshawa Committee of Adjustment [oshawa.ca] under section 53 of the Planning Act [ON].
You need it when: You want to create a new lot from your property in Oshawa.
Why is it needed?
- New lots (consents) go through the Committee of Adjustment [oshawa.ca].
- A building permit application is premature and will not be processed where the proposal requires Committee of Adjustment approval [oshawa.ca].
- Under section 53(14) of the Planning Act, you may appeal to the Ontario Land Tribunal if the approval authority does not give notice of a decision in time [ON].
When should you apply?
- Get the consent before you apply for a building permit on the new lot, because the City will not process a permit that needs Committee of Adjustment approval [oshawa.ca].
How long does review take?
Plan for about 64 business days. Planning Act, R.S.O. 1990, c. P.13, s. 53(14) [ON]
How do you submit it?
- The Oshawa Application Portal sends consent applicants to the Committee of Adjustment page [oshawa.ca].
Official pages
Track Consent to Sever: New Lot (Oshawa) free.