Building Permit: Complex Building, High-rise or High-hazard (Oshawa)
Building permit under Oshawa Building By-law 33-2009 for a complex building or addition, such as a high building or a high-hazard industrial building [oshawa.ca].
You need it when: You build or add to a complex building in Oshawa, such as a high building or a high-hazard industrial building.
Why is it needed?
- The City requires a building permit to construct any building or addition [oshawa.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
- The other approvals on the City's Applicable Law Checklist must be in place before a building permit can be issued [oshawa.ca].
When should you apply?
- Where your project needs it, get clearance from the Oshawa Executive Airport before the building permit is issued, using the Temporary Crane Permit Application [oshawa.ca].
- Get any rezoning, Committee of Adjustment approval, Official Plan amendment, site plan agreement or registered subdivision agreement first, because the City treats an application that still needs one as premature and will not process it [oshawa.ca].
- Pay the non-refundable Roadway Restoration Application Fee before the building permit is issued [oshawa.ca].
How long does review take?
Plan for about 30 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application on the Oshawa Application Portal [oshawa.ca]
- The submission items in the City's guide New Buildings and Additions Other Than Houses [oshawa.ca]
- Applicable Law Checklist [oshawa.ca]
- Energy Efficiency Design Forms [oshawa.ca]
- Commitment to General Review form, where it applies [oshawa.ca]
- Oshawa Executive Airport clearance, where it applies [oshawa.ca]
How do you submit it?
- Apply online through the Oshawa Application Portal (servicecv.oshawa.ca), where submitted applications are listed under My Items with their application number and status [oshawa.ca].
- Prepare drawings and files to the City's digital submission standards for permit applications [oshawa.ca].
What are the fees?
Building permit fees went up 3% on January 1, 2026, and the exact cost is calculated when you apply, using the fees in Building By-law 33-2009 from page 16 [oshawa.ca]. The non-refundable Roadway Restoration Application Fee is charged before the permit is issued [oshawa.ca].
Forms and guides
- Oshawa Building By-law 33-2009 (as amended by By-law 118-2025) (City of Oshawa, by-law)
- Oshawa Basic Building Permit Requirements (City of Oshawa, checklist)
- Oshawa Applicable Law Checklist (City of Oshawa, checklist)
- Oshawa New Buildings and Additions Other Than Houses (City of Oshawa, guide)
- Oshawa Energy Efficiency Design Forms (City of Oshawa, application form)
Official pages
- Building permits
- New buildings and additions other than houses
- Airport clearance (temporary crane permit) application
Track Building Permit: Complex Building, High-rise or High-hazard (Oshawa) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.