Draft Plan of Condominium (Oakville)
Draft plan of condominium approval in Oakville, where section 9 of the Condominium Act, 1998 applies the Planning Act section 51 approval process [ON].
You need it when: You plan a condominium development in Oakville and need draft plan of condominium approval.
Why is it needed?
- Section 9 of the Condominium Act, 1998 applies the Planning Act's section 51 approval process to draft plans of condominium [ON].
- The Town lists condominium among its planning applications [oakville.ca].
When should you apply?
- A development sign on the site needs proof of the Town's plan approval or building construction approval [oakville.ca].
- Other approvals may be needed before a building permit can be issued, depending on the project and where the property is [oakville.ca].
How long does review take?
Plan for about 86 business days. Planning Act, R.S.O. 1990, c. P.13, s. 51(34), applied by the Condominium Act, 1998 s. 9 [ON]
How do you submit it?
- The pages read do not say where to file. Start from the Town's Planning and Development Applications and Forms page [oakville.ca].
What are the fees?
See the Town's Planning and Development rates and fees schedule [oakville.ca].
Official pages
Track Draft Plan of Condominium (Oakville) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.