Road Occupancy Permit: Work, Hoarding, Cranes or Construction Access in the Road Allowance (Newmarket)
Road Occupancy Permit from Newmarket Public Works Services for work, hoarding, cranes or construction access in the Town road allowance, under Road Occupancy By-law 2018-31 [newmarket.ca].
Why is it needed?
- Road Occupancy By-law 2018-31 regulates the use, alteration and occupancy of highways in the Town [newmarket.ca].
- The permit covers utility installation, contractors installing municipal services under a site plan, subdivision or servicing agreement, lane closures for mobile cranes, scaffolding and hoarding, temporary construction access across the boulevard and heavy equipment trailers [newmarket.ca].
- Bins, PODs and material storage are not permitted on Town roads [newmarket.ca].
When should you apply?
- Notify Public Works 72 hours before work starts, using the Town's notice letter template [newmarket.ca].
- If your own contractor rebuilds the sidewalk after a Town curb cut, the contractor "must first obtain a Road Occupancy Permit (ROP)" [newmarket.ca].
- The pool page also requires a Road Occupancy Permit, through the Operations Department, for in-ground or on-ground pools or machinery over the Town boulevard [newmarket.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Road Occupancy Permit application form [newmarket.ca]
- Certificate of insurance for $5,000,000 liability naming the Town as Additional Insured [newmarket.ca]
- Traffic protection plan to OTM Book 7 [newmarket.ca]
- Security deposit [newmarket.ca]
- 72-hour notice letter, from the Town template [newmarket.ca]
How do you submit it?
- Apply to Public Works Services (Utility Services) at utilities@newmarket.ca [newmarket.ca].
What are the fees?
2026 fee: $188.90 per road segment for the permit, $220.40 per road segment for inspection, $57.53 for a revision or extension, and $718.37 per month for aerial crane trespass (Public Works Fees and Charges, Schedule C 2026) [newmarket.ca]. 2026 road degradation fee per m2: $500 for excavation under 1.2 m and $1,000 over 1.2 m, plus a surface fee from $56.57 for a surface under 2 years old down to $16.97 for one over 10 years old (Schedule C 2026) [newmarket.ca]. A security deposit is also required, and credit cards are not accepted for road or boulevard deposits [newmarket.ca].
Forms and guides
- Newmarket Public Works Fees and Charges, Schedule C 2026 (Town of Newmarket, fee schedule)
- Newmarket Road Occupancy By-law 2018-31 (Town of Newmarket, by-law)