Designated Structure Permit: Retaining Wall or Solar Panels (Newmarket)
Building permit from the Newmarket Building Division for a designated structure such as a retaining wall over 1 m high or solar panels, under the Ontario Building Code [ON].
You need it when: You build a retaining wall over 1 m high or install solar panels on a property in Newmarket.
Why is it needed?
- The Town lists retaining walls over 1 m in height and solar panels among work that needs a building permit [newmarket.ca].
When should you apply?
- Building permit fees must be paid at the time the application is submitted [newmarket.ca].
- Book inspections at inspections@newmarket.ca with two days' notice [newmarket.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application on the Development Portal [newmarket.ca]
- Site plan, elevations and sections [newmarket.ca]
- Drawings as unlocked, black and white PDFs with the submission date in the title block, with no fileshare links, .zip or .jpeg files [newmarket.ca]
- Schedule 1 Designer Information form and Applicable Law Declaration [newmarket.ca]
How do you submit it?
- Apply and track building permits on the Town's Development Portal at aca-prodca.accela.com/NEWMARKET [newmarket.ca].
- Building Division: building.permits@newmarket.ca, 905-953-5300 ext. 2400 [newmarket.ca].
What are the fees?
2026 fee: $200 for residential roof solar panels (Schedule I) [newmarket.ca]. The 2026 minimum application deposit (non-refundable) is $200 for a construction value of $50,000 or less, $500 for over $50,000 to $500,000 and $1,000 for all others (Schedule I) [newmarket.ca].
Forms and guides
- Newmarket Building Permit Fees and Charges, Schedule I 2026 (Town of Newmarket, fee schedule)
Official pages
Track Designated Structure Permit: Retaining Wall or Solar Panels (Newmarket) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.