Conditional or Partial Building Permit (Newmarket)
Conditional permit agreement or partial building permit issued in stages by the Newmarket Building Division, charged under the Town's 2026 Schedule I building permit fees [newmarket.ca].
You need it when: You need to start part of the work on a Newmarket building before the full building permit issues, or want the permit issued in stages.
Why is it needed?
- The Town's 2026 building permit fee schedule provides for conditional permit agreements and for partial permits issued by stage [newmarket.ca].
When should you apply?
- The Town's building pages give no separate steps for a conditional or partial permit, so ask the Building Division before you apply for the building permit [newmarket.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Conditional permit agreement with the Town [newmarket.ca]
How do you submit it?
- Building Division: building.permits@newmarket.ca, 905-953-5300 ext. 2400 [newmarket.ca].
- Building permit applications are made and tracked on the Town's Development Portal (Accela) [newmarket.ca].
What are the fees?
2026 fee: $1,000 per 100 m2 of gross floor area for a non-residential conditional permit agreement, or $1,000 per unit for a residential one, with a $5,000 minimum, and a partial permit surcharge of $1,000 per stage (Schedule I Building Permit Fees 2026) [newmarket.ca].
Forms and guides
- Newmarket Building Permit Fees and Charges, Schedule I 2026 (Town of Newmarket, fee schedule)
Official pages
Track Conditional or Partial Building Permit (Newmarket) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.