Building Permit: Large Building, Part 3 (Newmarket)
Building permit under the Ontario Building Code for a Part 3 building, such as an apartment, mid-rise, commercial or industrial building, from the Newmarket Building Division [newmarket.ca].
Why is it needed?
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
- The whole Town of Newmarket is a site plan control area under Planning Act s. 41, so site plan approval usually comes first [newmarket.ca].
When should you apply?
- Building permits are not typically accepted or issued until the site plan control requirements are addressed, because the whole Town is a site plan control area [newmarket.ca].
- The site plan agreement is generally executed after the site plan is approved [newmarket.ca].
- Where the project does not comply with the Zoning By-laws, a Zoning By-law Amendment is needed, decided by Council, and "If approved, there is a 20-day appeal period" [newmarket.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application on the Development Portal [newmarket.ca]
- Site plan, floor plans, elevations, sections and mechanical drawings as unlocked black-and-white PDFs with the submission date in the title block [newmarket.ca]
- Energy Efficiency Compliance Checklist for Part 3 (SB-10) [newmarket.ca]
- Schedule 1 Designer Information form and Applicable Law Declaration [newmarket.ca]
- Owner Commitment to General Review (GRCC) form [newmarket.ca]
How do you submit it?
- Apply and track the application on the Town's Development Portal (Accela), with drawings as unlocked black-and-white PDFs and no file-share links, .zip or .jpeg files [newmarket.ca].
- Building Division: building.permits@newmarket.ca, 905-953-5300 ext. 2400 [newmarket.ca].
What are the fees?
2026 fee: $26.27 per m2 for residential Part 3 mid-rise or high-rise buildings, with non-residential buildings charged per m2 by occupancy, for example assembly $21.40 and institutional $24.92 (Schedule I Building Permit Fees 2026) [newmarket.ca]. A non-refundable minimum application deposit applies: $200 for a construction value of $50,000 or less, $500 for over $50,000 to $500,000, and $1,000 for all others [newmarket.ca]. Development charges are calculated when the permit is issued [newmarket.ca].
Forms and guides
- Newmarket Building Permit Fees and Charges, Schedule I 2026 (Town of Newmarket, fee schedule)
Official pages
- Building and renovating in Newmarket
- Development documents and site plan control
- Building permit fees 2026 (Schedule I)
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.