Building Permit: Complex Building, High-rise or High-hazard (Newmarket)
Building permit under the Ontario Building Code for a high building, post-disaster building or high-hazard industrial building, applied for like any Part 3 building in Newmarket [newmarket.ca].
You need it when: You build a high building, a post-disaster building or a high-hazard industrial building in Newmarket, the complex building class of the Building Code.
Why is it needed?
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
- The whole Town of Newmarket is a site plan control area under Planning Act s. 41 [newmarket.ca].
When should you apply?
- Building permits are not typically accepted or issued until the site plan control requirements are addressed, because the whole Town is a site plan control area [newmarket.ca].
- If you need to start part of the work before the full permit issues, the Town's 2026 fee schedule provides for conditional permit agreements and partial permits by stage [newmarket.ca].
How long does review take?
Plan for about 30 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application on the Development Portal [newmarket.ca]
- Site plan, floor plans, elevations, sections and mechanical drawings as unlocked black-and-white PDFs with the submission date in the title block [newmarket.ca]
- Energy Efficiency Compliance Checklist for Part 3 (SB-10) [newmarket.ca]
- Schedule 1 Designer Information form and Applicable Law Declaration [newmarket.ca]
- Owner Commitment to General Review (GRCC) form [newmarket.ca]
How do you submit it?
- Apply and track the application on the Town's Development Portal (Accela), with drawings as unlocked black-and-white PDFs and no file-share links, .zip or .jpeg files [newmarket.ca].
- Building Division: building.permits@newmarket.ca, 905-953-5300 ext. 2400 [newmarket.ca].
What are the fees?
2026 fee: $26.27 per m2 for residential Part 3 mid-rise or high-rise buildings (Schedule I Building Permit Fees 2026) [newmarket.ca]. Non-residential buildings are charged per m2 by occupancy, and development charges are calculated when the permit is issued [newmarket.ca].
Forms and guides
- Newmarket Building Permit Fees and Charges, Schedule I 2026 (Town of Newmarket, fee schedule)
Official pages
- Building and renovating in Newmarket
- Development documents and site plan control
- Building permit fees 2026 (Schedule I)
Track Building Permit: Complex Building, High-rise or High-hazard (Newmarket) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.