Mississauga Road Occupancy Permit: Complex Construction
Road occupancy permit for multi-contractor construction next to a development site, managed through a Construction Management Plan [MISS].
You need it when: An approved development has complex or multiple construction operations by various contractors using the road allowance.
Why it's needed
- Coordinates all right-of-way use for a development (hoarding, gantries, crane swing, deliveries, lane closures) under one permit [MISS].
When to apply
- After the development approvals are in place and before site mobilization.
- Apply well in advance; the Construction Management Plan often goes through several comment cycles.
Review time
Plan for about 20 business days. estimate
Documents for a complete application
- Road Occupancy Permit application
- Construction Management Plan (CMP) [MISS]
- Certificate of Insurance: $10M general liability, $5M automobile, $5M environmental impairment, $5M aerial crane trespass, no XCU exclusion, pollution liability [MISS]
- Site logistics / staging drawings and traffic control plans
How to submit
- Email the application and documents to Transportation and Works Permit Administration Services: tw.pas@mississauga.ca (905-615-4950) [MISS].
Fees
Based on the type and extent of work under Schedule B-1 (Transportation and Works) of the User Fees and Charges By-law [MISS].
Forms and guides
- Mississauga Road Occupancy Permit General Conditions (City of Mississauga, standard / specification)
- Mississauga Road Occupancy Permit By-law (City of Mississauga, by-law)
- Mississauga Complex Construction Permit Application Checklist (City of Mississauga, checklist)
Official pages
Track Mississauga Road Occupancy Permit: Complex Construction free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.