Occupancy Prior to Completion (Partial Occupancy) (CoM)
Permission to occupy a building before it is complete, applied for on the Occupancy Prior to Completion Application under Building By-law 0236-2024.
You need it when: You want to occupy all or part of a building in Mississauga before construction is finished.
Why is it needed?
- Building By-law 0236-2024 Schedule D lists an occupancy permit inspection for an unfinished building [mississauga.ca].
- Schedule A 2026 sets a separate fee for occupancy before completion [mississauga.ca].
When should you apply?
- Give the Chief Building Official notice when the unfinished building is ready for its occupancy permit inspection (s. 39 and Schedule D) [mississauga.ca].
- For permits applied for in 2012 or later, request the occupancy permit by service request with your name, address and permit application number [mississauga.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Occupancy Prior to Completion Application [mississauga.ca]
- Name, address and building permit application number for the service request [mississauga.ca]
How do you submit it?
- The application form is on the City's building documents and forms page [mississauga.ca]. Request the occupancy permit by service request with your name, address and application number [mississauga.ca].
What are the fees?
2026 fees (Building By-law Schedule A): $22.66 per 100 m2 or part for non-residential, $141 per dwelling unit for residential, and $1,030 for a super tall building [mississauga.ca].
Forms and guides
- Mississauga Building By-law 0236-2024 (City of Mississauga, by-law)
- Mississauga Building By-law Schedule A 2026 Permit Fees and Refunds (City of Mississauga, fee schedule)
- Mississauga Occupancy Prior to Completion Application (City of Mississauga, application form)
Official pages
- Occupancy Prior to Completion Application
- Building documents and forms
- Book a building permit inspection
Track Occupancy Prior to Completion (Partial Occupancy) (CoM) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.