Permit Library › Other GTA municipalities › City of Mississauga › Building, demolition & signs (Planning and Building)
Conditional, Partial or Staged Building Permit (CoM)
Conditional, partial or staged building permit under Mississauga Building By-law 0236-2024 sections 8, 15 and 19, so approved parts of the work can start early.
You need it when: You need to start part of the work in Mississauga before the full building permit is issued, or to build in stages.
Why is it needed?
- The by-law says the scope of work for a permit "can be for all or part of a building" (s. 15) [mississauga.ca].
- A conditional permit application must state why the applicant believes unreasonable delays in construction would occur (s. 8) [mississauga.ca].
- A partial or conditional permit does not authorize construction beyond the work that was approved (s. 19) [mississauga.ca].
When should you apply?
- For a conditional permit, sign an agreement with the City (s. 8(3)) and give security to restore the site if final approvals are not obtained (s. 8(4)) [mississauga.ca].
- Each Stage 1 or Stage 2 permit is charged for its own stage, and construction cannot go beyond the work approved so far (s. 19) [mississauga.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application with the reasons unreasonable delays would occur (conditional permit) [mississauga.ca]
- Conditional permit agreement with the City [mississauga.ca]
- Security to restore the site if final approvals are not obtained [mississauga.ca]
How do you submit it?
- Apply to the Building Division, which takes building permit applications through ePlans [mississauga.ca]. Building permit inquiries: 311 or 905-615-4311 [mississauga.ca].
What are the fees?
2026 fees (Building By-law Schedule A): a conditional permit adds 20% of the permit fee, minimum $1,040, maximum $9,188, and $1,040 for each extension [mississauga.ca]. Stage 1 or Stage 2 permits are charged 50% of the calculated fee for each stage [mississauga.ca]. Partial permits are $453 each [mississauga.ca].
Forms and guides
- Mississauga Building By-law 0236-2024 (City of Mississauga, by-law)
- Mississauga Building By-law Schedule A 2026 Permit Fees and Refunds (City of Mississauga, fee schedule)
Official pages
Track Conditional, Partial or Staged Building Permit (CoM) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.