Conditional, Partial or Staged Building Permit (CoM)

Conditional, partial or staged building permit under Mississauga Building By-law 0236-2024 sections 8, 15 and 19, so approved parts of the work can start early.

You need it when: You need to start part of the work in Mississauga before the full building permit is issued, or to build in stages.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fees (Building By-law Schedule A): a conditional permit adds 20% of the permit fee, minimum $1,040, maximum $9,188, and $1,040 for each extension [mississauga.ca]. Stage 1 or Stage 2 permits are charged 50% of the calculated fee for each stage [mississauga.ca]. Partial permits are $453 each [mississauga.ca].

Forms and guides

Official pages

Track Conditional, Partial or Staged Building Permit (CoM) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.