Permit Library › Other GTA municipalities › Town of Milton › Building permits (Building Services)
Fire Protection Systems Permit: Sprinklers, Fire Alarm or Mag-locks (Milton)
Building Code Act permit from Milton Building Services for sprinkler systems, fire alarm systems and electromagnetic locks in ICI buildings [milton.ca].
You need it when: You install or alter a sprinkler system, fire alarm or electromagnetic locks in a Milton industrial, commercial or institutional building.
Why is it needed?
- The Town requires a building permit before any construction or renovation begins [milton.ca].
- The ICI fee table prices sprinklers, fire alarms and electromagnetic locks as their own permit items [milton.ca].
When should you apply?
- Get the permit before the system is installed or altered [milton.ca].
- The Town first checks the application for completeness and emails its acceptance or refusal, then invoices the fee, which is due on receipt before the full review begins [milton.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish, February 16, 2026 version [milton.ca]
- ICI permit application checklist [milton.ca]
- Schedule 1 Designer Information form [milton.ca]
- All drawings and forms as PDFs generated directly from CAD software, not scans, with printing and markups allowed [milton.ca]
How do you submit it?
- For an industrial, commercial or institutional (ICI) project, contact Building Services with the project address, then upload the permit package to the ShareFile link the Town sends [milton.ca].
- Building Services: 905-878-7252 ext. 2397, or the Town's building, zoning and planning contact form [milton.ca].
What are the fees?
Building Permits page ICI fees: $1/m² for sprinkler systems, $683.47 (flat rate) for a fire alarm, and $142.44 each for electromagnetic locks [milton.ca].
Forms and guides
- Milton Application for a Permit to Construct or Demolish (Town of Milton, application form)
- Milton Industrial, Commercial and Institutional Permit Application Checklist (Town of Milton, checklist)
- Milton Commitment to General Review Form (Town of Milton, application form)
- Milton Schedule 1 Designer Information Form (Town of Milton, application form)
Official pages
Track Fire Protection Systems Permit: Sprinklers, Fire Alarm or Mag-locks (Milton) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.