Building Permit Revision or Transfer (Markham)
Changes to an issued Markham building permit: revisions and supplementary submissions, transfer to a new owner, and extension past 12 months, under building fees By-law 2025-121 [markham.ca].
Why is it needed?
- Revisions, supplementary submissions and shop drawings are reviewed by Building Standards and charged by the hour [markham.ca].
- Building By-law 2024-206 has no stand-alone revocation clause and refers to the Building Code, but Schedule A, s. 5.14 lets you ask to defer revocation where construction has not seriously commenced within 12 months [markham.ca].
When should you apply?
- A deferral can keep the permit alive up to a maximum of 24 months from the date of permit issuance (Building By-law 2024-206, Schedule A, s. 5.14) [markham.ca].
- Complete ePLAN correction tasks within three months, or the City may treat the application as abandoned (s. 4.19) [markham.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Revised drawings, shop drawings or other supplementary submissions [markham.ca]
- Shop Drawing Certificate from the City's inspection forms, where shop drawings apply [markham.ca]
How do you submit it?
- All building permit applications must be submitted online through the City's ePLAN portal, and paper applications are no longer accepted [markham.ca].
- For a transfer or an extension request, contact Building Standards at buildingstandards@markham.ca or 905.475.4858 [markham.ca].
What are the fees?
2026 fees: revisions, supplementary submissions and shop drawings $131 per hour, form revisions $263, transfer of a permit to another owner $315, transfer of an application or change of address $315, adding contacts $131 per permit record, and extending a permit expiry date past 12 months 2x the permit fee (maximum $3,150) (By-law 2025-121) [markham.ca].
Forms and guides
- Markham Building Fees By-law 2025-121 (2026 fees) (City of Markham, fee schedule)
Official pages
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.