Permit Library › Other GTA municipalities › City of Markham › Planning applications and Committee of Adjustment (Planning and Urban Design)

Draft Plan of Condominium (Markham)

Draft plan of condominium approval for standard, common elements and vacant land condominiums, granted by City staff under delegated authority [markham.ca].

You need it when: You are creating a standard, common elements or vacant land condominium in Markham.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 86 business days. Planning Act, R.S.O. 1990, c. P.13, s. 51(34), applied by the Condominium Act, 1998 s. 9 [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

Set by Development Application Review Fee By-law 211-83, as amended 1 January 2026, with Schedule A updates effective March 24, 2026 [markham.ca].

Forms and guides

Official pages

Track Draft Plan of Condominium (Markham) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.