Change of Use Permit (Markham)
Change of use permit under Markham Building By-law 2024-206 section 4.15, applied for as a Non-Housing permit [markham.ca]. Provincial basis: Building Code Act section 10 [ON].
Why is it needed?
- Building By-law 2024-206 provides for change of use permits alongside construction and demolition permits [markham.ca].
- A change of property use also calls for a new Cross Connection Control Survey under Backflow Prevention By-law 2012-27 at ICI and multi-residential properties [markham.ca].
When should you apply?
- Check zoning before you apply, for example with a Zoning Search or Zoning Preliminary Review from Building Standards [markham.ca].
- The fee estimate must be paid in full before plans review begins, and any balance before the permit is issued [markham.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building and Land Use Declaration Form [markham.ca]
- Applicable Law Checklist [markham.ca]
- Schedule 1: Designer Information and the Permit Applicant Authorization form [markham.ca]
- Cross Connection Control Survey by a City-registered Qualified Person, where the backflow by-law applies [markham.ca]
How do you submit it?
- Apply online through ePLAN at eplanportal.markham.ca and follow the ePLAN Submission Standards, because paper applications are no longer accepted [markham.ca].
- Building Standards: buildingstandards@markham.ca, 905.475.4858 [markham.ca].
What are the fees?
2026 fees for alteration and change of use are per m2, for example $8.02 for business and personal services, $8.43 for other mercantile, $12.20 for a restaurant and $7.68 for industrial (By-Law 2025-121) [markham.ca]. The fee multiplier for the proposed occupancy is applied to the entire floor area (Building By-law 2024-206 Schedule A s. 2.18) [markham.ca].
Forms and guides
- Markham Building By-law 2024-206 (City of Markham, by-law)
Official pages
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.