Permit Library › Municipal: City of Toronto › Toronto Building › Building permits

Mechanical / HVAC Permit

Heating, ventilation and air-conditioning work in new or altered buildings.

You need it when: New or altered heating, ventilation or air-conditioning systems.

Why it's needed

When to apply

Review time

Plan for about 30 business days.

Documents for a complete application

Submission checklists

How to submit

Forms and guides

Official pages

Track Mechanical / HVAC Permit free.
Deadlines in business days, email alerts before decisions are due, and your whole team in one place.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.