Designated Structure Permit: Retaining Wall, Shoring, Crane Runway or Solar Panels (Halton Hills)
Building permit from Halton Hills Building Services for a retaining wall, shoring, a crane runway or a solar or wind installation, each priced in the 2026 Building Permit Fees [haltonhills.ca].
Why is it needed?
- The 2026 Building Permit Fees list retaining walls, shoring, crane runways and solar or wind installations as work with their own permit fees [haltonhills.ca].
- The Town's building permits page lists solar panels as work that needs a permit [haltonhills.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
When should you apply?
- Get the permit before you start the work. Starting construction without a permit costs 1.5 times the full permit fee under the 2026 Building Permit Fees [haltonhills.ca].
- Give Building Services at least two days' notice before each construction stage that needs an inspection (By-law 2016-0030 s. 14(2)) [haltonhills.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building Permit Application form [haltonhills.ca]
How do you submit it?
- Apply with the Building Permit Application form, which the Town's building permits page links on forms.haltonhills.ca [haltonhills.ca].
- Building Services is at Town Hall, 1 Halton Hills Drive (Building and Engineering Counter), 905-873-2600 ext. 2925, building@haltonhills.ca [haltonhills.ca].
What are the fees?
Retaining walls, shoring, crane runways and solar or wind installations each have their own fee in the 2026 Building Permit Fees [haltonhills.ca]. The 2026 minimum permit fee is $263.37 for small residential and $344.23 for other work, and it covers plans review and 2 inspections (2026 Building Permit Fees) [haltonhills.ca].
Forms and guides
- Halton Hills Building Permit Application (Town of Halton Hills, application form)
- Halton Hills 2026 Building Permit Fees (Town of Halton Hills, fee schedule)
Official pages
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.