Change of Use Permit (Halton Hills)
Change of use permit under Halton Hills Building By-law 2016-0030 (Schedule B row 6), issued by Building Services on its Change of Use Permit Application [haltonhills.ca].
You need it when: You change the use of a building or part of a building in Halton Hills.
Why is it needed?
- Building By-law 2016-0030 Schedule B sets a separate permit class for a change of use [haltonhills.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
When should you apply?
- Get the permit before you start the work. Starting construction without a permit costs 1.5 times the full permit fee under the 2026 Building Permit Fees [haltonhills.ca].
- Give Building Services at least two days' notice before each construction stage that needs an inspection (By-law 2016-0030 s. 14(2)) [haltonhills.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Change of Use Permit Application form [haltonhills.ca]
How do you submit it?
- File the Change of Use Permit Application form with Building Services [haltonhills.ca].
- Building Services is at Town Hall, 1 Halton Hills Drive (Building and Engineering Counter), 905-873-2600 ext. 2925, building@haltonhills.ca [haltonhills.ca].
What are the fees?
The 2026 change of use fee covers 3 hours of plans review and 2 hours of inspection, and the amount is set in Part A of the 2026 Building Permit Fees [haltonhills.ca]. Plans revisions cost $124.50 per hour in 2026 [haltonhills.ca].
Forms and guides
- Halton Hills 2026 Building Permit Fees (Town of Halton Hills, fee schedule)
Official pages
Track Change of Use Permit (Halton Hills) free.