Halton Region Municipal Consent (utilities)

Municipal consent issued at no charge by the Services Permit Group, emailed on issue [halton.ca].

You need it when: Local utilities placing plant in a Halton regional right-of-way.

Why it's needed

When to apply

Review time

Plan for about 20 business days. estimate

Documents for a complete application

How to submit

Fees

No charge [halton.ca].