Permit Library › Other GTA municipalities › Town of Georgina › Building permits (Building Division)
Designated Structure Permit: Retaining Wall, Solar Collectors or Tower (Georgina)
Building permit for a designated structure such as a retaining wall, rooftop solar or a tower, with fees set by Georgina Fees By-law 2026-0057 [georgina.ca].
You need it when: You build a retaining wall, put solar collectors on a building, or put up a tower or antenna in Georgina.
Why is it needed?
- Rooftop solar and rooftop generators need a building permit [georgina.ca].
- Solar needs a permit when it is on a building or provides hot water. Ground-mounted systems not tied to water or heating need none, and solar is exempt from zoning [georgina.ca].
- The Town's fees by-law sets building permit fees for retaining walls and for towers and antennas [georgina.ca].
When should you apply?
- Solar on a building needs a P.Eng. structural review and a commitment to general review with the application [georgina.ca].
- Radiocommunication and telecommunication tower siting is a separate Planning approval [georgina.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish (2026) and Schedule 1 Designer Information [georgina.ca]
- Solar Panel checklist (2026) [georgina.ca]
- P.Eng. structural review for solar on a building [georgina.ca]
- Commitment to General Review [georgina.ca]
How do you submit it?
- Apply through the Building Permit Application Portal at georgina.my.site.com, with every document as an unsecured PDF flattened to a single layer [georgina.ca].
- Building Division: building@georgina.ca, 905-476-4301 ext. 3007 [georgina.ca].
What are the fees?
2026 fees (Development Services Fees By-law 2026-0057, effective July 1, 2026): retaining wall $2.91/ft2, tower or antenna $456.00, solar on a house $184.00, other solar $531.00 [georgina.ca]. Radiocommunication tower siting review under the same by-law is $15,770 [georgina.ca].
Forms and guides
- Georgina Building By-law 2026-0058 (BU-1) (Town of Georgina, by-law)
- Georgina Development Services Fees By-law 2026-0057 (AD-5) (Town of Georgina, fee schedule)
- Georgina Application for a Permit to Construct or Demolish (2026) (Town of Georgina, application form)
- Georgina Schedule 1: Designer Information (Town of Georgina, application form)
- Georgina Solar Panel Checklist (2026) (Town of Georgina, checklist)
Official pages
Track Designated Structure Permit: Retaining Wall, Solar Collectors or Tower (Georgina) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.