Demolition Permit: House or Part 9 Residential Building (Georgina)
Demolition permit under Georgina Building By-law 2026-0058 (BU-1) to demolish all or part of a house, applied for on the same form as a building permit [georgina.ca].
You need it when: You demolish a house, or any residential building over 108 ft2 or with plumbing, in Georgina.
Why is it needed?
- A permit is needed to demolish any building over 108 ft2 or any structure with plumbing [georgina.ca].
- Demolishing a farm building needs no permit [georgina.ca].
When should you apply?
- Get LSRCA approval first where the land is regulated [georgina.ca].
- Where the building is connected to municipal services, the capping of utilities must be inspected [georgina.ca].
How long does review take?
Plan for about 10 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish (2026) [georgina.ca]
- Site plan or survey marking each structure "existing to remain unchanged" or "existing to be demolished" [georgina.ca]
- Letter of Authorization [georgina.ca]
- LSRCA approval where the land is regulated [georgina.ca]
How do you submit it?
- Apply on the Building Permit Application Portal at georgina.my.site.com, with all documents as unsecured PDFs flattened to a single layer [georgina.ca].
- Building Division: building@georgina.ca, 905-476-4301 ext. 3007 [georgina.ca].
What are the fees?
2026 fee: $304.00 for a Part 9 residential building, $184.00 for up to two residential accessory buildings and $77.00 for each additional building (Development Services Fees By-law 2026-0057) [georgina.ca].
Forms and guides
- Georgina Building By-law 2026-0058 (BU-1) (Town of Georgina, by-law)
- Georgina Development Services Fees By-law 2026-0057 (AD-5) (Town of Georgina, fee schedule)
- Georgina Application for a Permit to Construct or Demolish (2026) (Town of Georgina, application form)
- Georgina Letter of Authorization (Town of Georgina, application form)
Official pages
- Building permits information: demolition
- Building and demolition permit application form
- Building permits
Track Demolition Permit: House or Part 9 Residential Building (Georgina) free.