Change of Use Permit (Georgina)
Change of use permit under Georgina Building By-law 2026-0058 (BU-1), which the Town lists as work needing a permit [georgina.ca]. Provincial basis: Building Code Act section 10 [ON].
You need it when: You change the use of a building or part of a building in Georgina, even with little or no construction.
Why is it needed?
- The Town lists change of use among the work that needs a building permit [georgina.ca].
- A septic permit may also be needed for a change of use [georgina.ca].
When should you apply?
- Check zoning first, because zoning review is required for all building permit applications [georgina.ca].
- Site plan approval and entrances, LSRCA, Ministry of Transportation, MECP and heritage approvals come before permit issuance where they apply [georgina.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish (2026) and Schedule 1 Designer Information [georgina.ca]
- One digital site plan and one digital set of scaled drawings [georgina.ca]
- Letter of Authorization if the applicant is not the owner [georgina.ca]
- Septic permit documents where the change affects a septic system, including the Schedule 2 installer form [georgina.ca]
How do you submit it?
- Apply on the Building Permit Application Portal at georgina.my.site.com, with all documents as unsecured PDFs flattened to a single layer [georgina.ca].
- Building Division: building@georgina.ca, 905-476-4301 ext. 3007 [georgina.ca].
What are the fees?
2026 fee: $757.00 for a change of use, plus $184.00 per hour for after-hours review (Development Services Fees By-law 2026-0057) [georgina.ca].
Forms and guides
- Georgina Building By-law 2026-0058 (BU-1) (Town of Georgina, by-law)
- Georgina Development Services Fees By-law 2026-0057 (AD-5) (Town of Georgina, fee schedule)
- Georgina Application for a Permit to Construct or Demolish (2026) (Town of Georgina, application form)
- Georgina Schedule 1: Designer Information (Town of Georgina, application form)
- Georgina Commercial Building (ICI) Checklist (Town of Georgina, checklist)
Official pages
Track Change of Use Permit (Georgina) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.