Telecommunication Tower Concurrence (East Gwillimbury)
A telecommunication tower application under the Town's Telecommunication Tower Protocol, ending in a Council Letter of Concurrence, while ISED makes the final decision [eastgwillimbury.ca].
You need it when: You plan a telecommunication tower in East Gwillimbury and need the Town's concurrence before ISED decides.
Why is it needed?
- Council issues a Letter of Concurrence under the Telecommunication Tower Protocol [eastgwillimbury.ca].
- ISED makes the final decision on the tower [eastgwillimbury.ca].
When should you apply?
- Start with a pre-consultation, then staff check the application for completeness and a public information session is held [eastgwillimbury.ca].
- Council then considers the Letter of Concurrence [eastgwillimbury.ca].
- Notify the Town of ISED's decision before construction [eastgwillimbury.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Telecommunication Tower Application [eastgwillimbury.ca]
- Pre-Consultation Request Form [eastgwillimbury.ca]
How do you submit it?
- Complete the Telecommunication Tower Application. The Planning Branch handles it, Planning@eastgwillimbury.ca [eastgwillimbury.ca].
What are the fees?
2026 fee: $6,160.00 for a standard application and $542.70 for an exemption (Schedule A to Fees and Charges By-law 2015-078) [eastgwillimbury.ca].
Forms and guides
- East Gwillimbury Development Services Fees (Schedule A to Fees and Charges By-law 2015-078) (Town of East Gwillimbury, fee schedule)
Official pages
- Planning applications
- Telecommunication Tower Protocol (PDF)
- Telecommunication Tower Application (PDF)
Track Telecommunication Tower Concurrence (East Gwillimbury) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.