Sewer, Stormwater and Watermain Approval under the Town CLI-ECA (East Gwillimbury)
Town review of sanitary and storm sewer designs under its CLI-ECA in place of an MECP submission, with watermains recorded on Form 1, in East Gwillimbury [eastgwillimbury.ca].
Why is it needed?
- The Town holds a CLI-ECA, so sanitary and storm sewer designs are reviewed by the Town and not submitted to the MECP [eastgwillimbury.ca].
- Stormwater ponds serving more than 60 ha still go directly to the MECP [eastgwillimbury.ca].
- Watermains are recorded on Form 1 Record of Watermains with a General Services Plan [eastgwillimbury.ca].
When should you apply?
- The consultant must also get approvals from other authorities, such as the Region of York, MTO, MNRF, DFO, the Lake Simcoe Region Conservation Authority, CNR, Canada Post and utility companies [eastgwillimbury.ca].
- The Construction Management Plan must confirm whether a provincial permit to take water is required [eastgwillimbury.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Sanitary and storm sewer designs, with the Town's sanitary and storm sewer design sheets [eastgwillimbury.ca]
- Form 1 Record of Watermains with a General Services Plan [eastgwillimbury.ca]
- Construction Management Plan stating whether a permit to take water is needed [eastgwillimbury.ca]
- Designs meeting the Municipal Design Criteria and the Sanitary Sewer Commissioning Standards [eastgwillimbury.ca]
How do you submit it?
- Submit the designs to the Town's Development Engineering for review under the Engineering Standards and Design Criteria [eastgwillimbury.ca].
What are the fees?
2026 fee: $5,938.80 for a CLI-ECA review of sewers, or of an oil grit separator, LID or underground storage, and $8,337.10 for a stormwater management pond or a pumping station (Fees and Charges By-law 2015-078 Schedule I) [eastgwillimbury.ca]. Schedule I also lists a drinking water works application review for a watermain at $1,556.10 each, but the PDF text was partly scrambled, so confirm the amounts with the Town [eastgwillimbury.ca].
Official pages
- Engineering Standards and Design Criteria
- Municipal Design Criteria
- Water and wastewater fees (Schedule I)