Occupancy Permit Prior to Completion (East Gwillimbury)
Permit to occupy a building, or part of one, before it is complete, issued by the Building Standards Branch under Building By-law 2019-058 section 7 [eastgwillimbury.ca].
You need it when: You want to occupy all or part of a building in East Gwillimbury before construction is complete.
Why is it needed?
- Building By-law 2019-058 s. 7 governs occupancy permits, and s. 7.2 allows partial occupancy of a building [eastgwillimbury.ca].
- The Town's Building Resources page has an Application for Permit to Occupy a Building Prior to Completion [eastgwillimbury.ca].
When should you apply?
- Apply before anyone occupies the unfinished building, or the part of it to be used [eastgwillimbury.ca].
- If more than six months have passed since the occupancy permit was issued, you must apply again (By-law 2019-058 s. 7.3) [eastgwillimbury.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Application for Permit to Occupy a Building Prior to Completion (Town form) [eastgwillimbury.ca]
- Agent Authorization Form, where an agent applies for the owner [eastgwillimbury.ca]
How do you submit it?
- The form is on the Town's Building Resources page, and building permit applications go through the CityView Portal at cityview.eastgwillimbury.ca/cityviewportal [eastgwillimbury.ca].
- Ask the Building Standards Branch how to file it, at Building@eastgwillimbury.ca or 905-478-4282 x 1261 [eastgwillimbury.ca].
What are the fees?
Occupancy permit: $200.00 (Building Permit Fees, Schedule C to By-law 2019-058, Section H, no year stated) [eastgwillimbury.ca].
Forms and guides
- East Gwillimbury Building By-law 2019-058 (Town of East Gwillimbury, by-law)
- East Gwillimbury Building Permit Fees (Schedule C to By-law 2019-058) (Town of East Gwillimbury, fee schedule)
Official pages
- Building resources and forms
- Application to occupy a building before completion (PDF)
- Building By-law 2019-058 (PDF)
Track Occupancy Permit Prior to Completion (East Gwillimbury) free.