Permit Library › Other GTA municipalities › Region of Durham › Regional roads

Region of Durham Municipal Consent (utilities)

Approval for utility plant in the regional right-of-way; a Road Occupancy Permit is also needed. Valid for one year [DUR].

You need it when: A utility company, agency, municipality or private party with a Municipal Access Agreement installs or relocates infrastructure in a Durham regional right-of-way.

Why it's needed

When to apply

Review time

Plan for about 40 business days. apply 60 days ahead [DUR]

Documents for a complete application

How to submit

Fees

$312.63 plus HST up to 20 m; $871.25 plus $1/m over 20 m; no charge for relocations forced by Region projects (2026) [DUR].

Official pages

Track Region of Durham Municipal Consent (utilities) free.
Deadlines in business days, email alerts before decisions are due, and your whole team in one place.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.