Permit Library › Other GTA municipalities › Town of Caledon › Roads and right-of-way (Operations)
Municipal Consent for Utility Installations (Caledon)
Town of Caledon Municipal Consent for new utility installations in the Town right-of-way, reviewed by the Public Utility Coordinating Committee (PUCC) under Municipal Access Agreements [caledon.ca].
You need it when: You install a new utility in a Town of Caledon road right-of-way.
Why is it needed?
- The Public Utility Coordinating Committee (PUCC) reviews applications for new utility installations in the Town right-of-way [caledon.ca].
- Council-approved Municipal Access Agreements set the terms for granting Municipal Consents and Road Occupancy Permits for utility work [caledon.ca].
When should you apply?
- The PUCC reviews the application for a new utility installation in the Town right-of-way, so apply before the installation [caledon.ca].
- Utility work in the right-of-way may also need a Road Occupancy Permit under the Municipal Access Agreement [caledon.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Utility installation application on the Town Survey123 form [caledon.ca]
How do you submit it?
- Submit through the Town Survey123 form [caledon.ca].
- PUCC submissions: toc.pucc.submissions@caledon.ca [caledon.ca].
What are the fees?
2026 fee: $506 plus $0.55 per m after 300 m (2026 Fees By-law 2025-105, Schedule L) [caledon.ca]. Re-inspection is $160 and re-submission is $210 [caledon.ca].
Forms and guides
- Caledon 2026 Fees By-law 2025-105 (Town of Caledon, fee schedule)
Official pages
Track Municipal Consent for Utility Installations (Caledon) free.