Heavy Truck Road Use (Haul) Permit (Caledon)
Heavy Truck Road Use (Haul) Permit from the Town of Caledon for hauling fill on Town roads, with a per-load road use charge set in the 2026 Fees By-law [caledon.ca].
You need it when: You haul fill by heavy truck on Town roads in Caledon.
Why is it needed?
- Hauling fill on Town roads needs a Haul Permit from the Town [caledon.ca].
- During Half Load Season loads are limited to 5 tonnes per axle, from March 1 to April 30 on hardtop roads and from March 1 to May 15 on gravel roads [caledon.ca].
When should you apply?
- Hauling on Regional roads also needs a Region of Peel excess load permit [caledon.ca].
- A Caledon fill permit application needs a letter from Public Works and Engineering confirming that road damage securities are posted, plus the Region of Peel excess load permit where it applies [caledon.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Online Haul Permit form [caledon.ca]
- Region of Peel excess load permit for any Regional roads on the route [caledon.ca]
How do you submit it?
- Apply with the online Haul Permit form on forms.caledon.ca [caledon.ca].
- Half Load Season questions go to Service Caledon at 905.584.2272 x.7750 [caledon.ca].
What are the fees?
2026 fee: $750.00 plus $2.71 per load per lane km (2026 Fees By-law 2025-105, Schedule K) [caledon.ca].
Forms and guides
- Caledon 2026 Fees By-law 2025-105 (Town of Caledon, fee schedule)
Official pages
Track Heavy Truck Road Use (Haul) Permit (Caledon) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.