Fill Permit / Site Alteration (Caledon)

Fill permits under the Site Alteration By-law. They can be issued, for example, when a building permit exists, for agricultural improvement (up to 10,000 m³ imported), or to store topsoil for a development with conditional site plan approval [caledon.ca].

You need it when: Placing or removing fill, altering grade, or storing or removing topsoil in Caledon.

Why it's needed

When to apply

Review time

Plan for about 30 business days. estimate; public notice for large sites

Documents for a complete application