Change of Use Permit (Caledon)

Change of use (change of occupancy) permit from Caledon Building Services under Building By-law 2025-117 and section 10 of the Building Code Act [caledon.ca].

You need it when: You change how a building or unit in Caledon is used, such as a new occupancy in an existing space, with or without construction.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee for interior alterations or change of occupancy: $5.64 per m2 for Group C and D, $5.38 per m2 for Groups A, B, E and F (Fees By-law 2025-105) [caledon.ca]. Hourly review items, which include change of use, are $115.00 per hour with a minimum that depends on the item [caledon.ca].

Forms and guides

Official pages

Track Change of Use Permit (Caledon) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.