Building Permit: Complex Building, High-rise or High-hazard (Caledon)
Building permit under Caledon Building By-law 2025-117 for a high-rise, hotel, mixed-use or high-hazard building, applied for with the Town's high-rise checklist [caledon.ca].
Why is it needed?
- The Town has a separate checklist for new high-rise, hotel and mixed-use buildings and additions [caledon.ca].
- The Building Code treats high buildings, post-disaster buildings and high-hazard industrial buildings as complex buildings [ON].
- All land in Caledon is a Site Plan Control Area, and commercial, industrial and institutional projects need site plan approval [caledon.ca].
When should you apply?
- Get site plan approval first. The final approval package then goes to Building Services so it can issue the permit [caledon.ca].
- Non-residential development charges are payable at building permit issuance, and parkland cash-in-lieu is payable before the building permit is issued [caledon.ca].
- To start excavation, shoring or foundations early on an ICI project, ask for a conditional or phased permit [caledon.ca].
How long does review take?
Plan for about 30 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish (2026) [caledon.ca]
- New/Addition High Rise, Hotel and Mixed-Use checklist [caledon.ca]
- Commitment to General Reviews by Architects and Professional Engineers form [caledon.ca]
- Applicable Law Declaration and Land and Building Use Declaration [caledon.ca]
- Final site plan approval package [caledon.ca]
How do you submit it?
- Apply online through the Construction Companion portal or the Building Services online form, because the Town accepts building permit applications online only [caledon.ca].
- Questions go to Building Services at buildingpermits@caledon.ca or 905-584-2272 ext. 2233 [caledon.ca].
What are the fees?
2026 fee per m2: $16.61 for multi-unit residential, $22.93 for hotels, Group D office $18.02 shell or $21.62 finished, Group E retail $16.47 shell or $20.59 finished and parking garages $8.24, with a $321 minimum for Groups A, B, D, E and F (2026 Fees By-law 2025-105) [caledon.ca]. Permits over $5,150.00 can be paid 50% at application and the balance at issuance [caledon.ca].
Forms and guides
- Caledon Building By-law 2025-117 (Town of Caledon, by-law)
- Caledon 2026 Fees By-law 2025-105 (Town of Caledon, fee schedule)
- Caledon Application for a Permit to Construct or Demolish (2026) (Town of Caledon, application form)
- Caledon Applicable Law Checklist (Town of Caledon, checklist)