Pre-Consultation Meeting (Burlington)
A pre-consultation meeting with Burlington Community Planning that comes before major development applications: OPA, rezoning, subdivision, site plan and consent [burlington.ca].
You need it when: You are preparing an Official Plan amendment, rezoning, plan of subdivision, site plan or consent application in Burlington.
Why is it needed?
- The City's 2026 Development Application Fees place pre-consultation before major applications [burlington.ca].
- The Development Applications page says a pre-consultation is required before a consent application [burlington.ca].
- Conservation Halton decides at the pre-consultation stage whether it has an interest in the application [burlington.ca].
When should you apply?
- Hold the pre-consultation before you file the OPA, rezoning, subdivision, site plan or consent application [burlington.ca].
- Allow for the City's lead time: "It takes four to six weeks from the time we receive your submission until the meeting" [burlington.ca].
- File the application within one year of the meeting date to have the fee credited [burlington.ca].
How long does review take?
Plan for about 30 business days. City guidance [burlington.ca]
What documents does a complete application need?
- Pre-consultation Request Form [burlington.ca]
How do you submit it?
- Complete the City's Pre-consultation Request Form, linked from the Development Applications page [burlington.ca].
What are the fees?
2026 fee: $2,295.00, credited to a future application filed within one year of the pre-consultation meeting date (2026 Development Application Fees) [burlington.ca]. Additional meetings are charged and not credited [burlington.ca].
Forms and guides
- Burlington 2026 Development Application Fees (City of Burlington, fee schedule)
- Burlington Pre-consultation Request Form (City of Burlington, application form)
Official pages
Track Pre-Consultation Meeting (Burlington) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.