Permit Library › Other GTA municipalities › City of Burlington › Planning applications, zoning clearance and Committee of Adjustment (Community Planning)

Consent to Sever, Easement or Lot Line Adjustment (Burlington)

Consent from Burlington's Committee of Adjustment to sever land, adjust a lot line or grant an easement, under section 53 of the Planning Act [burlington.ca] [ON].

You need it when: You want to create a new lot, adjust a lot line or set up an easement on land in Burlington.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 64 business days. Planning Act, R.S.O. 1990, c. P.13, s. 53(14) [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: $9,270.00 for a minor consent (lot line adjustment or easement), and $11,940.00 for lot creation plus $3,150.00 per additional buildable lot (2026 Development Application Fees) [burlington.ca]. Region of Halton fee: $1,340.51 [burlington.ca]. 2026 fee: $2,295.00 for pre-consultation, $3,255.00 for major revisions, $1,430.00 for minor revisions, $725.00 for a deferral, $1,715.00 for validation of title (Region of Halton $310.87) and $65.00 for the certificate [burlington.ca].

Forms and guides

Official pages

Track Consent to Sever, Easement or Lot Line Adjustment (Burlington) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.