Permit Library › Other GTA municipalities › City of Burlington › Building permits (Building Department)
Conditional Building Permit (Burlington)
Conditional building permit, listed in class G of Burlington's building fee Schedule A to By-law 18-2025 and charged at 20% of the full permit fee [burlington.ca].
You need it when: You ask the Building Department in Burlington for a conditional building permit ahead of the full building permit.
Why is it needed?
- Schedule A to By-law 18-2025 lists conditional permits under class G, with a fee of 20% of the full permit fee [burlington.ca].
- Work started before a permit is issued carries its own charge in the same class [burlington.ca].
When should you apply?
- On a residential lot with ten or fewer dwelling units, the Grading and Drainage Clearance Certificate is required before any building permit is issued [burlington.ca].
- Start work within six months of issue, or the permit may be revoked under section 8 of the Building Code Act [burlington.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application, sent by email to the Building Department [burlington.ca]
- Large-file transfer request for submissions over 20 MB [burlington.ca]
How do you submit it?
- Ask the Building Department at 905-335-7731 about a conditional permit [burlington.ca].
- Building permit applications go by email to buildingpermits@burlington.ca [burlington.ca].
What are the fees?
20% of the full permit fee (Schedule A to By-law 18-2025) [burlington.ca].
Forms and guides
- Burlington Building Permit Fee Schedule A to By-law 18-2025 (City of Burlington, fee schedule)
- Burlington Building Permit By-law 030-2026 (City of Burlington, by-law)
Official pages
Track Conditional Building Permit (Burlington) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.