Building Permit: Small Building, Part 9 (Burlington)
Building permit under Building Permit By-law 030-2026 for new construction or an addition to a small ICI building that falls under Part 9 of the Ontario Building Code [burlington.ca].
Why is it needed?
- The City lists industrial, commercial and institutional new construction and additions as a building permit type [burlington.ca].
- Part 9 buildings other than houses include small commercial or industrial buildings, stacked townhouses and farm buildings under O. Reg. 163/24 [ON].
When should you apply?
- If the project needs site plan approval, it starts with a pre-consultation, and the City says "It takes four to six weeks from the time we receive your submission until the meeting" [burlington.ca].
- Start work within six months of issue, or the permit may be revoked under section 8 of the Building Code Act [burlington.ca].
How long does review take?
Plan for about 15 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application, sent by email to the Building Department [burlington.ca]
- Large-file transfer request for submissions over 20 MB [burlington.ca]
- Re-submissions by email with the subject "Building Permit Re-submission - <app no.> - <address>" [burlington.ca]
How do you submit it?
- Email the application to buildingpermits@burlington.ca with the subject line "Building Permit Application - <address>". Paper applications are not accepted [burlington.ca].
- Check the status of an application by phone at 905-335-7731 (Building Department, 426 Brant St.) [burlington.ca].
What are the fees?
Fees for new buildings, additions and mezzanines are in class A of Schedule A to By-law 18-2025, with a minimum fee of $377.00 for all work unless otherwise indicated [burlington.ca]. If site plan approval is needed, the 2026 pre-consultation fee is $2,295.00, credited to a future application within one year of the meeting, and a major site plan costs $12,200.00 plus a variable fee, with a Region of Halton fee of $1,340.51 [burlington.ca].
Forms and guides
- Burlington Building Permit Fee Schedule A to By-law 18-2025 (City of Burlington, fee schedule)
- Burlington Building Permit By-law 030-2026 (City of Burlington, by-law)
Official pages
- Applying for a building permit
- Building permit fee Schedule A (PDF)
- Development applications and pre-consultation
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.