Permit Library › Other GTA municipalities › City of Burlington › Building permits (Building Department)
Building Permit: Interior Alteration or Unit Finish (Burlington)
Building permit under Building Permit By-law 030-2026 for an ICI unit finish or interior alteration, or for rack and shelf storage, both listed City permit types [burlington.ca].
You need it when: You finish a unit or alter the interior of an industrial, commercial or institutional building in Burlington, or add rack and shelf storage.
Why is it needed?
- The City lists ICI unit finish or interior alteration, and rack and shelf storage, as building permit types [burlington.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
- If the work changes how the space is used, change of use is a separate ICI permit type [burlington.ca].
When should you apply?
- If the new tenant's use differs from the old one, read the City's Change of Use guide before you apply [burlington.ca].
- Start work within six months of issue, or the permit may be revoked under section 8 of the Building Code Act [burlington.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application, sent by email to the Building Department [burlington.ca]
- Large-file transfer request for submissions over 20 MB [burlington.ca]
- Re-submissions by email with the subject "Building Permit Re-submission - <app no.> - <address>" [burlington.ca]
How do you submit it?
- Email the application to buildingpermits@burlington.ca with the subject line "Building Permit Application - <address>". Paper applications are not accepted [burlington.ca].
- Check the status of an application by phone at 905-335-7731 (Building Department, 426 Brant St.) [burlington.ca].
What are the fees?
Building permit fees are set by Schedule A to By-law 18-2025, with a minimum fee of $377.00 for all work unless otherwise indicated [burlington.ca]. Racking falls under fee class A [burlington.ca].
Forms and guides
- Burlington Building Permit Fee Schedule A to By-law 18-2025 (City of Burlington, fee schedule)
- Burlington Building Permit By-law 030-2026 (City of Burlington, by-law)
Official pages
Track Building Permit: Interior Alteration or Unit Finish (Burlington) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.