Permit Library › Other GTA municipalities › City of Burlington › Building permits (Building Department)
Building Permit: New House, Addition or Additional Residential Unit (Burlington)
Building permit for a new house, an addition or an additional residential unit, issued by the Building Department under Building Permit By-law 030-2026 [burlington.ca].
You need it when: You build a new house, put an addition on a house, or create an additional residential unit in Burlington.
Why is it needed?
- The City lists new dwellings, additions, additional dwelling units, interior renovations, basement finishes and tiny houses among its residential building permit types [burlington.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
When should you apply?
- Low-density residential permits first need the Pre-Building Approval Application, which covers zoning clearance, grading and drainage, and forestry review [burlington.ca].
- By-law 052-2018 requires a Grading and Drainage Clearance Certificate before any building permit is issued for work on a residential lot with ten or fewer dwelling units [burlington.ca].
- Install the erosion and sediment controls listed in the grading Application Status Report before construction starts [burlington.ca].
How long does review take?
Plan for about 10 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application, sent by email to the Building Department [burlington.ca]
- Pre-Building Approval Application with the Zoning Clearance Certificate and Grading and Drainage Clearance Certificate [burlington.ca]
- Grading and Drainage Plan stamped by a P.Eng. or O.L.S., following the City's Grading and Drainage Checklist [burlington.ca]
- Large-file transfer request for submissions over 20 MB [burlington.ca]
How do you submit it?
- Email the application to buildingpermits@burlington.ca with the subject line "Building Permit Application - <address>". Paper applications are not accepted [burlington.ca].
- Check the status of an application by phone at 905-335-7731 (Building Department, 426 Brant St.) [burlington.ca].
What are the fees?
Building permit fees are set by Schedule A to By-law 18-2025, with a minimum fee of $377.00 for all work unless otherwise indicated [burlington.ca]. The grading certificate fee and security are paid by e-transfer or EFT before the certificate is issued [burlington.ca].
Forms and guides
- Burlington Building Permit Fee Schedule A to By-law 18-2025 (City of Burlington, fee schedule)
- Burlington Building Permit By-law 030-2026 (City of Burlington, by-law)
Official pages
Track Building Permit: New House, Addition or Additional Residential Unit (Burlington) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.