Site Plan Approval (Brampton)
Site Plan Approval under section 41 of the Planning Act and Site Plan Control By-law 96-86, reviewed as a Limited, Basic or Full Site Plan Review [brampton.ca].
Why is it needed?
- Site Plan Approval is required before a building permit is issued [brampton.ca].
- The City reviews site plans as a Limited, Basic or Full Site Plan Review, and Mature Neighbourhood Areas review covers additions, new or replacement detached dwellings of 50 m2 or more and detached garages [brampton.ca].
- Section 41 of the Planning Act lets the City control site plans [ON].
When should you apply?
- Start with a pre-application consultation (PAC), booked for the next available Tuesday afternoon time slot after a preliminary technical review [brampton.ca].
- Staff then issue a Notice of Conditional Approval, and Legal Services prepare any Site Plan Agreement [brampton.ca].
- Site Plan Approval must be in place before the building permit is issued, and the City keeps a security holdback of at least 10% through a one-year maintenance period [brampton.ca].
How long does review take?
Plan for about 43 business days. Planning Act, R.S.O. 1990, c. P.13, s. 41(12) [ON]
What documents does a complete application need?
- Site plan application through BramPlanOnline [brampton.ca]
- Site Plan Agreement, prepared by Legal Services after the Notice of Conditional Approval [brampton.ca]
- Securities, with at least a 10% holdback through the one-year maintenance period [brampton.ca]
How do you submit it?
- Apply online through BramPlanOnline, the City's portal for planning applications [brampton.ca].
What are the fees?
Base $29,720, to a maximum of $91,842 (Planning fee By-law 85-96, Schedule A) [brampton.ca]. Limited site plan $4,000 and minor revision $4,000 [brampton.ca]. Each resubmission past the third $5,110 [brampton.ca]. The 2026 building permit fee schedule lists $1,336.09 for site plan approval with one temporary structure agreement [brampton.ca].
Forms and guides
- Brampton Development Application Fees, Schedule A (City of Brampton, fee schedule)
Official pages
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.