Permit Library › Other GTA municipalities › City of Brampton › Planning applications and Committee of Adjustment (Development Services)
Part Lot Control Exemption (Brampton)
An exemption by-law that removes part lot control under section 50(7) of the Planning Act for lots or blocks in a registered Brampton plan [brampton.ca].
You need it when: You want to create lots or blocks within a registered plan in Brampton, or maintenance easements, by removing part lot control.
Why is it needed?
- Part lot control is lifted for a registered plan by an exemption by-law under section 50(7) of the Planning Act [ON].
- The City charges per registered plan and per lot or block created, with a separate fee for maintenance easements [brampton.ca].
When should you apply?
- The fee is charged per registered plan, so the application is for land in a plan that is already registered [brampton.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Part Lot Control application form [brampton.ca]
How do you submit it?
- Complete the City's Part Lot Control application form. The City takes planning applications through BramPlanOnline [brampton.ca].
What are the fees?
$3,118 per application per registered plan plus $242 per lot or block created (Planning fee By-law 85-96, Schedule A) [brampton.ca]. Maintenance easements $3,118 [brampton.ca].
Forms and guides
- Brampton Development Application Fees, Schedule A (City of Brampton, fee schedule)
Official pages
Track Part Lot Control Exemption (Brampton) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.