Draft Plan of Subdivision (Aurora)

Draft plan of subdivision approval under section 51 of the Planning Act, processed by Aurora's Development Planning Division, with Development Engineering reviewing the engineering [aurora.ca].

You need it when: You are dividing land in Aurora into lots or blocks through a plan of subdivision.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 86 business days. Planning Act, R.S.O. 1990, c. P.13, s. 51(34) [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: $53,243 base, including registration of the subdivision agreement, plus a residential processing fee of $571 to $930 per unit and $11,271 per hectare, or $11,037 per hectare for non-residential (Fees and Charges By-law 6737-25, Schedule H) [aurora.ca]. 2026 fee: revision $3,040, revisions to a draft approved plan or conditions of draft approval $7,288, extension of draft approval $3,817, and subdivision without units $15,000 (Schedule H) [aurora.ca]. Engineering fees are 7.9% of servicing costs (Schedule B) [aurora.ca].

Official pages

Track Draft Plan of Subdivision (Aurora) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.