Sewage System (Septic) Permit (Aurora)
Sewage system permit from the Aurora Building Division under section 11 of Building By-law 6096-18, for new, altered or decommissioned on-site systems [aurora.ca].
You need it when: You install, alter or decommission a septic tank or other on-site sewage system on a property in Aurora.
Why is it needed?
- Building By-law 6096-18 s. 11 sets out the sewage system permit [aurora.ca].
- Schedule G of the 2026 Fees and Charges By-law charges new systems, alterations, headers, and tank removal or decommissioning [aurora.ca].
- The Ontario Building Code, O. Reg. 163/24, regulates sewage systems in every Ontario municipality [ON].
When should you apply?
- Fees are payable in full when you apply (Building By-law 6096-18 s. 19.1) [aurora.ca].
- If the work also needs a Site Alteration Permit for fill or a grade change, that application asks for records of any well or septic decommissioning [aurora.ca].
- Arrange locates through Ontario One Call before digging [aurora.ca].
How long does review take?
Plan for about 10 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Permit application to the Building Division [aurora.ca]
How do you submit it?
- Apply through the CityView Portal at cvportal.aurora.ca, by email to building@aurora.ca, or on a USB drive in person [aurora.ca].
- Building Division: building@aurora.ca, (365) 500-2081, Town Hall, 100 John West Way [aurora.ca].
What are the fees?
2026 fees: a new system up to 200 m2 is $687 per system, and over 200 m2 is $5.00 per m2 to a maximum of $3,932 (Fees and Charges By-law 6737-25, Schedule G) [aurora.ca]. An alteration to a sewage disposal system is $328, and headers, tank removal or decommissioning are $328 each [aurora.ca].
Forms and guides
- Aurora Building By-law 6096-18 (office consolidation, as amended) (Town of Aurora, by-law)
- Aurora Building Permit Fee Handout 2026 (Town of Aurora, fee schedule)
Official pages
Track Sewage System (Septic) Permit (Aurora) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.