Permit Library › Other GTA municipalities › Town of Aurora › Building permits (Building Division)
Building Permit Revision, Transfer or Reactivation (Aurora)
Revision to a permit (section 13) or transfer of a permit to a new owner (section 23) under Aurora Building By-law 6096-18, and permit reactivation under 2026 Schedule G [aurora.ca].
You need it when: You change the plans for an Aurora building permit, need the permit transferred to a new owner, or need a permit reactivated.
Why is it needed?
- Building By-law 6096-18 sets out revisions to a permit in s. 13 and transfers of a permit in s. 23 [aurora.ca].
- An application that remains inactive for six months after it is made may be deemed abandoned under s. 14.1 [aurora.ca].
When should you apply?
- Apply for a transfer when the property changes owners, using the Town's Permit Transfer Application [aurora.ca].
- A refund request must be made no later than six months after a withdrawal, abandonment, refusal or revocation request (Building By-law Schedule D) [aurora.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Permit Transfer Application, for a new owner [aurora.ca]
How do you submit it?
- Building applications go to the Building Division through the CityView Portal at cvportal.aurora.ca, by email to building@aurora.ca, or on a USB drive in person [aurora.ca].
- Building Division: building@aurora.ca, (365) 500-2081 [aurora.ca].
What are the fees?
2026 fee: $345 per application for a revision to permit plan (up to 3 hours of review), $137 per application for a transfer of permit, and $194 per permit for reactivation (Fees and Charges By-law 6737-25, Schedule G) [aurora.ca]. Review of plans is $137 per hour [aurora.ca].
Forms and guides
- Aurora Building By-law 6096-18 (office consolidation, as amended) (Town of Aurora, by-law)
- Aurora Building Permit Fee Handout 2026 (Town of Aurora, fee schedule)
Official pages
Track Building Permit Revision, Transfer or Reactivation (Aurora) free.