Minor Variance (Aurora)

A minor variance from Aurora Zoning By-law 6000-17, decided by the Town's Committee of Adjustment using the four tests in section 45(1) of the Planning Act [aurora.ca].

You need it when: Your Aurora project does not meet the Zoning By-law exactly and you need relief before you can get a building permit.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 21 business days. Planning Act, R.S.O. 1990, c. P.13, s. 45 [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: $3,353 for ground-related residential, $2,801 for Oak Ridges Moraine residential, $4,108 for all other uses including industrial, commercial and institutional, and $5,350 for non-owner-occupied or after-construction applications (Fees and Charges By-law 6737-25, Schedule H) [aurora.ca]. 2026 fee: $1,686 for a recirculation (Schedule H) [aurora.ca]. 2026 fee: $103 for the zoning review of a Committee of Adjustment application (Schedule B) [aurora.ca].

Forms and guides

Official pages

Track Minor Variance (Aurora) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.